Summer 2017/2018 Projects (Active)
Project Delivery Method: |
Lease-Lease Back |
Architects: |
Dougherty & Dougherty, GkkWorks, Rachlin Partners
|
Contractor: |
Various |
|
|
|
|
Project Phase: |
|
|
|
100% |
100% |
100% |
90% |
Design |
Bid & Award |
Construction |
Closeout |
|
|
|
|
The Summer 2017 Projects include the following scope of work:
HVAC Project (Active)
Project Delivery Method: |
Lease-Lease Back
|
Architect: |
Dougherty and Dougherty
|
Contractor: |
Envise
|
|
|
|
|
Project Phase: |
|
|
|
100% |
100% |
100% |
100% |
Design |
Bid & Award |
Construction |
Closeout |
|
|
|
|
This project includes installation of HVAC units in classroom buildings at El Rincon Elementary School.
Energy Conservation Program (Proposition 39) (Completed)
Project Delivery Method: |
Design-Build |
Contractor: |
Climatec LLC
|
|
|
|
|
Project Phase: |
|
|
|
100% |
100% |
100% |
100% |
Design |
Bid & Award |
Construction |
Closeout |
|
|
|
|
The Energy Conservation Program (Proposition 39) includes the following scope of work:
- Installation of new high efficiency HVAC units
- Upgrading of interior & exterior LED Lighting
- Installation of dual technology occupancy sensors
- Installation of smart programmable thermostats
- Integration of occupancy sensors
Phase I Projects (Completed)
Project Delivery Method: |
Lease-Lease Back |
Architects: |
Rachlin Partners, Dougherty & Dougherty
|
Contractor: |
Balfour Beatty Construction
|
|
|
|
|
Project Phase: |
|
|
|
100% |
100% |
100% |
100% |
Design |
Bid & Award |
Construction |
Closeout |
|
|
|
|
The Phase I Projects includes the following scope of work:
- Exterior Painting
The exterior of the school will be painted in the new school colors. This project is complete.
- New Playgrounds
The playground improvement project at El Rincon Elementary School includes the installation of new playground surfaces and equipment for both kindergarten and elementary school children. The new play equipment will provide a number of age-appropriate activities including elevated platforms, slides and swings. Shade canopies will also be provided and will be integrated with the play equipment. New color-matching rubber play surfaces will also be installed to provide fall protection in compliance with current safety guidelines. This project is complete.
- New Bicycle & Skateboard Racks
This project includes the installation of new bicycle and skateboard racks throughout the campus and has been completed.
- Video Surveillance
Conduit, cable and video surveillance cameras will be installed campus wide. This project is complete.
- Replace 2nd Floor Deck Waterproofing
The existing deteriorated exterior decks at the second story of the two story building will have a new waterproof surface installed. This project is complete.
- Fire Alarm Repairs
Remove and replace weather damaged fire alarm conduit lines. This project is complete.